At Whitsett Avenue and Valley Spring Lane, the street work around the old Weddington Golf & Tennis property was scheduled to wrap up at the end of October. Harvard-Westlake's construction update dated October 30, 2026, said the permit work on Whitsett should be finished by Saturday, October 31. It also said Valley Spring and Whitsett would return to normal traffic and the fencing would go back to the perimeter. In the same update, the school reported crews installing artificial turf and assembling metal bleachers at the field and pool. The field and tennis-court lights had been tested on October 19, with shutoffs at 8 p.m. and 9 p.m.
That site sits on the Zev Yaroslavsky LA River Greenway. The improvements now heading to Studio City's stretch of the river follow one pattern. The work with dollar amounts and deadlines is being paid for by private developers as conditions of their city approvals. The neighborhood council's own river plans are still at the stage of volunteer requests and feasibility studies. If you walk this path, the order in which things open follows directly from that.
Harvard-Westlake's River Park is the closest to opening. At the Studio City Neighborhood Council's October 28 meeting, Ari Engelberg of Harvard-Westlake said construction was about 99% complete. He said the public amenities were expected to open around March 1, 2027, and that community open houses were planned. That date has already moved once. In August, the Harvard-Westlake Chronicle reported that the planned fall 2026 opening had been pushed to early 2027, pending city occupancy approval and final inspections.
The school's River Park FAQ explains public access in plain terms:
"The 6-acre park and clubhouse will be open to the general public every day of the year from 7 a.m. until 9 p.m. The River Park will be accessible from the Zev Yaroslavsky LA River Greenway and through the main pedestrian / visitor entrance to the River Park campus, off of Whitsett Avenue."
The city's 2023 approval record lists 5.4 acres of publicly accessible open space, with landscaped paths connecting to the Zev Greenway. The athletic facilities work on a different schedule from the park, because the school gets them first. The FAQ says Harvard-Westlake will generally use them from 1 p.m. to 8 p.m. during the school year, mostly between 3 p.m. and 7 p.m. The public windows fit around that:
For a walker, the most useful part of the approval isn't inside the campus at all. City Planning's response says the school must improve and maintain the Zev Greenway along the river from Whitsett Avenue to the project's western property line. It must also install a controlled pedestrian crossing at Whitsett Avenue and Valleyheart Drive. In practice, a private campus is responsible for upkeep of a stretch of public river path and for a safer crossing at one of the busiest entry points to the Greenway.
Parking also matters for anyone who drives to the path. The school lists 386 underground spaces and 17 surface spaces, all entered from Whitsett. Its stormwater system is designed to hold 350,000 gallons of runoff for reuse on site.
A short distance west along Ventura Boulevard, the next set of river money comes from a residential project. Urbanize LA reported that the Los Angeles City Council upheld approval of Riverwalk at Studio City at 12555 Ventura Boulevard and rejected the appeals filed against it. Riverwalk is a joint venture of Genton Property Group, RC Development and Torino Companies. It calls for 814 apartments, about 76,000 square feet of commercial space, and more than 800 parking spaces on four underground levels.
According to the same report, Councilmember Nithya Raman supported the project because of the river access it provides and its commitment to keep the 1950s bowling-alley sign that still stands on the property. Urbanize LA also reported that the project team agreed to $675,000 in additional community benefits for river access and tree planting.
At the October 28 neighborhood council meeting, Scott Mandell, chair of the council's Riverwalk Development Ad Hoc Committee, listed what that negotiation produced. He said the City Council approved the project on October 21, 2026. The conditions he described:
The first two items add up to the $675,000 Urbanize LA reported. The timing is much longer than at River Park. The draft minutes say construction could begin in 2027 and finish around 2033, depending on approvals or litigation. River Park is measured in months, and Riverwalk is measured in years, but both work the same way. A private landowner wanted something from the city, and the river path improved as part of the deal.
The neighborhood council's own river actions at the same October 28 meeting show the other side of the pattern. All three are requests. None of them spends money.
The first motion supports restoring, beautifying and connecting the Greenway. It also supports naming the stretch between Whitsett Avenue and Laurel Canyon Boulevard for the environmental advocate Melanie Winter. Winter founded The River Project and spent decades pushing for a more natural Los Angeles River, as the Los Angeles Times recorded in 2025. At the meeting, board member Chip Meehan cited her work to establish the river as a protected navigable waterway.
The second motion asks the city for right of entry so volunteers can do cleanup and invasive-species removal on that same Whitsett-to-Laurel Canyon stretch. The minutes record board discussion of access, city coordination and insurance, and they state that no expenditure was authorized. The council already has volunteers. Its outreach committee reported a recent cleanup that drew 40 to 45 people.
The third motion asks Council District 4 to look into acquiring, or partnering on, the parcels at 11575 and 11571 Ventura Boulevard for parkland and a future entrance to the Greenway. Supporters called the parcels a rare possible access point. The vote was divided, and the motion asks only for a feasibility discussion. No purchase was authorized.
The Colfax Avenue end of the river is also under discussion. In May 2026, the council asked Councilmember Raman for fencing and "No Trespassing" signs on the south side of the river, from the Colfax pedestrian bridge to the rear of the underpass. The request asked for coordination with city and county agencies and with homelessness outreach. At the October meeting, the Council District 4 field deputy said a proposed fence near the bridge was still under discussion. Security fencing and safety improvements for the Colfax Bridge were on the agenda for the November 10 Sustainability and Beautification Committee meeting. The same agenda included planning for "100 Trees for 100 Years," a tree-planting initiative for the Studio City centennial.
Arranged by date, every item that has a schedule is either a city park building or a private project's obligation. The council's river ideas come last:
Several of those undated items cover the same Whitsett-to-Laurel Canyon stretch that the two private projects are now funding and maintaining. Once River Park opens and Riverwalk's conditions are carried out, the volunteers, the proposed name and the proposed new entrance will be added to a path that private projects have already paid to improve.
I watch projects like River Park and Riverwalk closely because they change how a neighborhood works day to day long before they appear in any market report. If you'd like to understand how the coming changes along the Studio City river corridor could affect a home you own or are considering nearby, Larry Calemine would be glad to walk through it with you. Schedule a private consultation.
With more than 20 years of experience in the greater Los Angeles Real Estate market, Larry Calemine has the experience and vision necessary to ensure the successful completion of your next Real Estate transaction. Larry’s vast knowledge of the current market and strong negotiation skills will assure anyone the best possible experience.